Construction Updates

Print
Press Enter to show all options, press Tab go to next option

2021 CONSTRUCTION UPDATES

Welcome to our Construction Updates page, new for 2021. Here, we will be posting regular updates on larger construction projects in the City that affect our residents, such as any underground work that re-routes traffic, any major paving projects with detours or lane restrictions, etc. 


DOWNTOWN POWER LINE CONVERSION -Completed


1ST AVE NW & CHAPLIN ST. - Completed


2021 PAVING AND CONCRETE PROGRAM - Completed

Projects have begun for the season. Please be aware that any schedules are subject to change due to weather and other scheduling factors. Affected residents WILL receive notice from the contractor prior to work beginning. You may also have been the recipient of this CONSTRUCTION NOTICE to your mailbox, which was distributed for pre-construction information. 

Locations for the 2021 program were selected from the condition assessment database that were all identified as being in very poor condition. Each project takes approximately 2 to 3 weeks. 

Identified projects (click on each title for a work area map) include:

PAVING & CONCRETE PROJECTS- Completed 
6th Ave NW (N. Railway to Cheadle) - remove & replace concrete curb and repave roadway -COMPLETE
2nd Ave NW (Cheadle to Chaplin) - remove & replace sidewalk on East side, patch roadway - COMPLETE 
Chaplin St. Bridge - repave the driving surface -COMPLETE
9th Avenue NE (Connaught to Sidney) - storm water catch basin replacement, sidewalk spot repairs, repave roadway - COMPLETE
Golden Place - storm water catch basin replacement, sidewalk spot repairs, repave roadway COMPLETE
Jubilee Drive - storm water catch basin replacement, sidewalk spot repairs, repave roadway COMPLETE
Downtown Lane - 100 blk lane between 1st Ave NE and 2nd Ave NE - repave alley COMPLETE
3rd Ave SE (McIntosh to Friesen) - sidewalk spot repairs and repave roadway COMPLETE


FRIESEN STREET STORM SEWER MEEP FUNDED PROJECT: MAY 25, to SEPT - Now in PHASE 5! - Updated Sept 17

The objective of this project is to decommission the existing storm pipes located in private property and reinstall a new storm sewer down public roadways and lanes. The old storm sewer in residential yards will be decommissioned by filling the pipe with low-strength concrete. This will be a relatively unobtrusive process with minimal disturbance to residents. Construction activities will damage the street within the City right-of-way; therefore, asphalt repairs and replacement of the curb and sidewalk is included.   

Completing this project will eliminate risks associated with the pipe running through private yards, allow better access to the sewer for maintenance, and improve the performance of the stormwater infrastructure. 

Acknowledgement: The City would like to recognize the funding support for this project from the Province of Saskatchewan’s Municipal Economic Enhancement Program (MEEP). 

Click here for Phase 1 Detour Map May 25 - June 7 
Click here for Phase 2 Detour Map June 7 to June 21
Click here for Phase 3 Detour Friesen Street June 12 
Click here for Phase 4 Friesen Street June 25 - July 30 
NEW: Click here for Phase 5 Friesen Street Aug 1 - Sep 10 - Paving and sidewalk repairs completed. Landscaping to be completed soon.  - latest update as of September 17th. 


ON NOW 
ACTIVE TRANSPORTATION EXPANSION PROJECT please see: Active Transportation Expansion Project 


CREEK BANK STABILIZATION -Completed

The Creek Bank Stabilization project is now completed along the southside of the Swift Current Creek near Riverside Park.
(See Map)
 


OTHER PROJECTS COMING SOON:

#7 Lift Station Forcemain Installation - to accommodate sanitary flows from new development & the Water Treatment Plant residuals, a new forcemain will be installed adjacent to Memorial Drive (from Hillcrest Drive to 600 m South) 


 

 Paving Notice Flyer